Desert Palm Apartments Overview Report

Exclusively available on IvyPanda Available only on IvyPanda

Executive Summary

Desert Palm apartments are 1, 2, and 3 bedroom apartments in the middle of the city designed for the modern city dwellers. The apartments will be situated in the heart of Nairobi the market target being middle-income young professionals. The apartments will be located in a fast-paced environment and will have a secured underground parking.

We will write a custom essay on your topic a custom Report on Desert Palm Apartments Overview
808 writers online

The Project comprises an apartment block in the middle of the city. The apartment block shall comprise 3 No. 1-Bedroom units, 3 No. 2-Bedroom units and 2 No. 3-Bedroom units. In addition to this, each unit shall have 2 designated parking lots situated below the apartment at an underground level.

Business Objectives

  • To increase MJ holdings market share in Nairobi
  • To provide affordable yet quality accommodation for city dwellers and to alleviate the persistent problem of insufficient housing in the city
  • To build a sustainable and profit oriented business in Nairobi that will help the business grow and expand
  • To enhance our reputation as the leading developer in East Africa by investing in competitive ventures
  • Successfully providing competitive infrastructure using our team of qualified professionals

MJ holding is capable in providing housing solutions as is evident from the numerous projects successfully undertaken over the years that have contributed to our knowledge and innovation. MJ holdings intends on increasing its market share by 30 percent and increasing profits by 25 percent and Desert Palm apartments will help catapult the company to this goal.

Business Vision: To provide competitive affordable housing and parking facilities within the city centre that remains relevant at all times ensuring stable and sustainable profits to investment

Project Management Objectives

  • To manage time in a project allowing it to commence on a specific starting point and end in a specific predetermined time
  • To control the cost and resources to complete the project within the given budget
  • To instill a sense of direction so as to ensure commitment, this includes motivation, teamwork and developing confidence.
  • To act as a change agent who introduces innovations and overcomes resistance to necessary change that is beneficial to the project as a whole.

A need arises for project management in this project due to:

  • There is unfamiliarity: the project being in the middle of the city in a crowded place. It would therefore require the services of a project manager to decipher and tackle the challenges that arise with great creativity and innovation.
  • The project context is a rapidly changing environment due to the crowded nature and possibly shortage of space within the site to act as temporary storage of building materials and equipment. A project management structure thereby becomes suitable due to its flexibility and diversity.
  • The reputation of the organization undertaking the development is at risk. This is due to the complex nature of the target market that would find the apartment less attractive should it fail to be completed within a reasonable amount of time. The failure to complete the project would also result into a financial loss to the stakeholders and compromise future opportunities in terms of relationship with financing bodies.

Solution to Business Objectives

  • Provision of Parking within the apartment (at basement level: 2 car parks per unit) increases the value of the apartment and it would thus make it attractive to the target market and as a result the period of recouping investment would be shortened.
  • Provision of 1-bedroom, 2-bedroom and 3-bedroom units gives a diversified products thereby maximizing on the market attract the required demand.
  • By manipulating design variables, the interplay between the different units, their diversified nature and ample parking space gives a niche to the project over similar nature allowing investors to enjoy returns throughout the life cycle of the project (Lock p.234).

Project management Solution/ Description

  • Time will be managed through creation of a structure that outlines a schedule in which activities/ milestones are best performed in order to complete the project in the required time. This is achieved through analysis of the various processes involved in construction using Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT). Activities which can thus run concurrently are scheduled to run that way so as to save on time.
  • With project complexity in terms of number of subcontractors involved in carrying out the project, the project management team provides direction by motivating the parties involved. The project manager also acts as the entrepreneur in the project in terms of mobilizing resources, facilities and human resources.

Project Description

MJ ltd intends on constructing middle income apartments targeting young professionals, Desert Palm will consist of one, two and three bedroom apartments that will cater to the economic need of the target population as well as desire for a sanctuary in the ever-busy streets of Nairobi.

Upon the successful completion of Desert Palm, we project an increase in the profit margin by 15% and market share increase by 9%. Moreover, we will achieve trust in potential consumers and respect among our competitors and shareholders.

1 hour!
The minimum time our certified writers need to deliver a 100% original paper

The project includes the erection of three blocks consisting of one, two and three bedroom apartments. Due to constraint of space (Crowded City), project management presents opportunities that allow the organization to move fast through a flexible and diverse project management structure. Desert palm Apartments is faced by a risk, time and financial constraint. The project is to be tackled in a manner that would ensure a minimum of this constraint. Complexity arises with the number of contractors working on the project. All these contractors depend on each other for materials, and service. It becomes paramount to ensure smooth running of operations among these contractors.

The impact of this project includes retaining workers and establishment of a sustainable profit oriented development. Measures of the project success include the completion of the project within the budget, time limit and without extreme strain on human resource. Assuming that there are no unexpected problems arising (Philips p.354)

The Roles of the employees and Project Stakeholders are as follows

Project Sponsor
MJ Holdings Ltd
Provides executive team approval and sponsorship for the project. Has budget ownership for the project and is the major stakeholder and recipient for the project deliverables.
Project OwnerProvides policy definition to the Project team. Resolves all policy issues with the appropriate policy owners in order to provide a clear, decisive definition. Makes final decisions and resolves conflicts or issues regarding project expectations across organizational and functional areas. The project owner and the project manager have a direct link for all communication. The project manager will work directly with the project owner on all policy clarification.
Project ManagerProvides overall management to the project. Accountable for establishing a Project Charter, developing and managing the work plan, securing appropriate resources and delegating the work and insuring successful completion of the project. All project team members report to the project manager. Handles all project administrative duties, interfaces to project sponsors and owners and has overall accountability for the project.
Steering CommitteeProvide assistance in resolving issues that arise beyond the project manager’s jurisdiction. Monitor project progress and provide necessary tools and support when milestones are in jeopardy.
StakeholderKey provider of requirements and recipient of project deliverable and associated benefits. Deliverable will directly enhance the stakeholders’ business processes and environment. Majority of stakeholders for this project will be agency heads, CIO’s and project management representatives.
Team MemberWorking project team member who analyzes, designs and ultimately improves or replaces the business processes. This includes collaborating with teams to develop high level process designs and models, understanding best practices for business processes and partnering with team members to identify appropriate opportunities, challenging the old rules of the business and stimulating creating thinking, and identifying organizational impact areas.

The identity of the stake holders are as follows.

NameRole
MJ HoldingsProject Sponsor
MJ HoldingsProject Owner
Samson JamesProject Manager
Edward JohnsSteering Committee Member
Mary KateSteering Committee Member
Ibrahim YusufSteering Committee Member
Nimrod Isaacs’Team Member

Project Approach

By phasing the project, First putting up the 3- Bedroom Units within the apartment then proceeding to do build the rest of the apartment (Ireland p.110). This may attract the Target clientele for the 3-Bedroom units to pre-purchase the units before actual completion of the units. This would amount to extra funding to carry the project to completion. It would be safe to assume that the target clientele for the 3-bedroom units would be a family who may have accumulated adequate savings and would be keener to purchase a unit. Their counterparts are either fresh graduates or young couples who would be looking to rent a 1-bedroom unit or a 2-bedroom unit.

Project Estimates

Estimated Schedule

Key Project milestones relative to project start are as follows:

Project MilestonesdurationTarget Date
Project StartMM/DD/YY
Excavation30 days1stJan 2010
Blinding to foundation, hardcore fills5 days6thJan 2010
Laying of reinforcement to basement, necessary waterproofing and column reinforcements10 days16thJan 2010
Concrete foundation at basement level5 days21stJan 2010
Laying of reinforcements for ramps to basement and columns to upper basement levels (laying of ducting for mechanical and electrical services_5 days26thJan 2010
Concrete works on columns and ramps3 days29thJan 2010
Form works for suspended floor levels and the necessary reinforcements and ducts for required mechanical and electrical services10 days8thFeb 2010
Concreting suspended floors (in the event of double basement or ground floor in the event of single basement)5 days13thFeb 2010
Reinforcements for columns5 days (for each floor)29thFeb 2010
Concreting of ground floor columns3 days(for each floor)16thMarch2010
Construction of ground floor walling10 days( for each floor)4thApril 2010
Reinforcement of necessary beams and suspended floor slab together with formwork and necessary services10 days (for each floor)21stJune 2010
Concreting suspended floor5 days (for each floor)21stJuly 2010
Shuttering for columns and suspended floors to roof slab20 days15thAug 2010
Roof structure42 days19thSept 2010
Roof covering12 days1stOct 2010
Electrical and mechanical (first fix)100 days15thJan 2011
Door frames15 days30thJan 2011
Window fixing15 days15thFeb 2011
Plastering of ground floor walling and any other walls in suspended floors5 days(for each floor)29thMarch 2011
Painting first coat20 days20thApril 2011
Floor screed10 days (per floor)30thMay 2011
Wall and floor tiles30 days1stJune 2011
Joinery works50 days20thJuly 2011
Electrical second fix30 days20thAug 2011
Plumbing second fix50 days4thOct 2011
Wall renderings and claddings30 days4thNov 2011
Doors and iron monger30 days4thDec 2011
Final coat of painting30 days4thJan 2012
Project Completion5thJan 2012

Resource Requirements – Team and Support Resources

The following personnel resources are required to complete this project:

Personnel Resource TypesQuantity
Building contracters3
Interior designers1
Supplier3
Total Personnel Resources7

Assuming that they work within the expected time schedule

Remember! This is just a sample
You can get your custom paper by one of our expert writers

Estimated Cost

ExpenseOriginal BudgetCurrent BudgetSpent to DateEst. to CompleteCurrent ForecastVariance
Walling, partitions and all external works12,298,478.0014,913,698.0012,205,860.00
Finishes and services30,325,400.0036,186,816.0034,903,456.00
Building structure16,923,800.0019,753,377.0019,668,250.00
Other
Total64,633,436.0075,003,112.0074,059,376.00

Assuming that there are no major unexpected accidents.

Checkpoint/ Funding Schedule

Funding will be received upon completion of every phase as per the project expectations. Thorough assessments will be carried out and a detailed financial statement will be required.

Project Controls

Steering Committee Meetings

Steering committee meetings will comprise of the officials from MJ Holdings and the contractors. the purpose of these meetings will be to monitor progress and to solve any problems that may arise during the construction.

Monthly Status Reports

Monthly Status reports will be handed to the owners and stakeholders in an attempt to monitor progress.

Issue Management

All Project-related issues will be tracked, prioritized, assigned, resolved, and communicated in accordance with the Project Management Procedures. The Project manager is assigned this task and is required to communicate these issues with the owners.

Change Management

With such site context, changes may have to be effected to allow for steady progression of the construction. This may pose a challenge due to number of parties involved. The project manager therefore would introduce innovations that would result in necessary change and at the same time overcome any resistance that may arise. The project manager will analyse all changes before implementation and reviewed by MJ Holdings inorder to determine its effects on budget and time.

Communication Management

The project manager would act as a centre of communication between the parties involved. He would receive all the results, requests, memoranda and complains. He would also give out information to subordinates and all stakeholders on matters such as policies, budgets, objectives and schedules on a weekly basis; however. The project manager will also provide status report to MJ holdings on a monthly basis and distributes the project team meeting minutes. MJ Holdings on all urgent issues, these issues include time and financial constraint. Steering committee meetings and monthly status reports will also be carried out to ensure communication between all parties involved.

Authorizations

The Scope Statement will be approved by:

We will write
a custom essay
specifically for you
Get your first paper with
15% OFF

The Project Manager: Samson James

The Project Owner: MJ holdings Ltd

The Project Sponsor: MJ Holdings Ltd

Project Changes will be approved by:

MJ Holdings Ltd

Project deliverables will be approved/accepted by:

The Project Owner: MJ Holdings Ltd

The Project Sponsor: MJ Holdings Ltd

The key Stakeholders: MJ Holdings Ltd

Specific task responsibilities of project resources will be defined in the Project/work Plan.

Scope Statement Approval Form/Signatures

Project Name: Desert Palm Apartments

Project Manager: Samson James

I have reviewed the information contained in this Scope Statement and agree.

NameSignatureDate
Samson James
Edward Johns
Mary Kate
Ibrahim Yusuf
Nimrod Isaacs

The signatures of the people above relay an understanding in the purpose and content of this document by those signing it. By signing this document, you agree to this as the formal Project Scope Statement.

Works Cited

  1. Ireland, Lewis. Project Management. Washington: McGraw-Hill Professional, 2006. Print.
  2. Lock, Dennis. Project management. Surrey: Gower Publishing, 2007. Print.
  3. Phillips, Joseph. PMP Project Management Professional Study Guide. Washington: McGraw-Hill Professional, 2003. Print.
Print
Need an custom research paper on Desert Palm Apartments Overview written from scratch by a professional specifically for you?
808 writers online
Cite This paper
Select a referencing style:

Reference

IvyPanda. (2021, December 24). Desert Palm Apartments Overview. https://ivypanda.com/essays/desert-palm-apartments-overview/

Work Cited

"Desert Palm Apartments Overview." IvyPanda, 24 Dec. 2021, ivypanda.com/essays/desert-palm-apartments-overview/.

References

IvyPanda. (2021) 'Desert Palm Apartments Overview'. 24 December.

References

IvyPanda. 2021. "Desert Palm Apartments Overview." December 24, 2021. https://ivypanda.com/essays/desert-palm-apartments-overview/.

1. IvyPanda. "Desert Palm Apartments Overview." December 24, 2021. https://ivypanda.com/essays/desert-palm-apartments-overview/.


Bibliography


IvyPanda. "Desert Palm Apartments Overview." December 24, 2021. https://ivypanda.com/essays/desert-palm-apartments-overview/.

Powered by CiteTotal, online bibliography tool
If you are the copyright owner of this paper and no longer wish to have your work published on IvyPanda. Request the removal
More related papers
Cite
Print
1 / 1