Inter Process Communications Communication Plan Term Paper

Exclusively available on Available only on IvyPanda® Written by Human No AI

Overview

This communication strategy addresses a wide range of IPC-Next business needs with a number of communication activities that ensure the successful completion of the project. On the most basic level, the IT department will work on the logo design, implementation of an inventory management system, IT support, and software maintenance. These innovations will be used to rationalize the resource scheduling process to leverage cost-effective tools, aimed at the improved communication process across departments. On a more global scope, the IPC-Next will gain scalability for future business growth by expanding its operational efficiency.

Internal and external customers will benefit from the newly established dashboard with extended resources on availability, turnover, and schedule which will benefit the waste elimination and limited financial expenditures. This communication plan neither includes common goals for specific stakeholder groups nor addresses particular approaches and assumptions necessary to meet the project’s main objectives. Instead, it effectively outlines the purpose, target audience, and format of the communication activity. By strictly adhering to the communication strategy described below, the team is likely to avoid moral confusion and productivity issues, contributing to the project’s successful implementation.

Escalation and feedback

For this communication plan, several escalation routes are in place dependent on the types of issues and resolutions needed. First, critical service and support issues related to urgent requests from sponsors or IHP clients should be prioritized over other problems. If appeared, such discrepancies should be sent directly to the IPC Manager or IT Director based on the nature and scope of the issue. Instead, minor problems should be handled directly by the PM team, staff, and faculty on behalf of the company’s representatives. The priority of the issue should be determined on the basis of its impact on the revenue and the business’s reputation.

Yet, the timelines of communication resolution should be clearly explained to all the employees, clients, and sponsors regardless of their priority. Feedback should be given in a variety of forms depending on the employees’/clients’ preference, setting, and convenience of the method. Appropriate methods include email, conference calls, in-person meetings, and group meetings. Interviews and interaction with the media, regardless of the medium (TV, print, digital), should be handled by PR professionals first. Transparency, friendly attitude, and honesty constitute key components of public communication.

Responsibility and authority

Most of the responsibilities and authority in terms of communication activities provided in this communication plan belong to the project manager and his team. This professional is responsible for daily, weekly, and monthly meetings with team members to conduct program component status meetings, program reviews, periodic demos, and target presentations. The project manager also oversees high-quality communications to the component team members in the form of in-person meetings and digital messages.

Apart from the aforementioned activities, the plan includes events aimed at meeting with sponsors, discussing the project’s strategy with the steering committee, reviewing the program’s decisions, lessons learned, future benefits, risks, and realizations of the project. For such incidents, the role of an overseer is assigned to the IPC Manager/Director. The authority, in this case, is the IPC President who does not necessarily participate in the discussions of executive leadership but makes final adjustments to the decision-making process.

Communication activities

WhatWho/TargetPurposeWhen/FrequencyType/Method(s)
Program Kick-off MeetingPM team; MGH IHP CIFO; IPC manager; IPC Director; IHP clientsTo introduce the scope of the project; to confirm the main objectives and deliverable goalsOnce at the beginning of the projectMeeting.
Stage-Gate ReviewMGH IHP Manager; MGH IHP Director; PM team; IPC ManagerTo divide the project into distinct stages separated by decision points and delegate tasksOnce at the beginning of the projectMeeting
Program Component Status Reports and ReviewPM team; IPC Manager; MGH IHP Manager; IHP clientsTo provide guidance on program status reporting; to describe the overview of the best practices, requirements, and activities; to update leadership on the project statusMonthly – first Tuesday of every monthConference call
Component Status MeetingsPM team; MGH IHP Faculty; MGH IHP StaffTo review the project’s status, achieved milestones, key issues; to adjust the schedule, change requestsMonthly – first Thursday of every monthMeetings; emails; conference calls (as needed)
Subteam working meetings or discussionsPM team; MGH IHP Faculty; MGH IHP Staff; Information Technology (IT) DirectorTo review the project’s status within specific teamsWeekly – every MondayMeetings
Sponsor MeetingsPM team; IPC Manager; MGH IHP Manager; MGH IHP ProvostTo meet with the project sponsor to discuss the project status; to get approval for changes to Project PlanMonthly – first Wednesday of every monthConference call; in-person meeting as needed
Steering Committee MeetingsMGH IHP President; MGH IHP CIFO; MGH IHP Director; IP Vice-Provost; MGH IHP ProvostTo direct a project; to control the achievement of project outcomes; to ensure delivery of the project outputsTwice per scope of the project (at the beginning and in the middle)In-person meeting
Program ReviewMGH IHP Manager and PM team with all stakeholdersTo identify the produced deliverables; to determine the success of the project in terms of meeting the declared objectivesQuarterlyIn-person meeting
Periodic Demos and Target PresentationsPM team; IHP clients; MGH IHP Manager; MGH IHP Faculty; MGH IHP StaffTo gain input from specific groups; to keep teams informed of the Project’s statusAs soon as critical milestones of the project are met; Monthly/quarterlyPresentation; meeting; discussion
Communications to component team membersPM team; target to be determined by the PM team as neededTo maintain effective professional communication within the organizationDaily/Weekly/Monthly (depending on the activity)Email lists, home page announcements, conference calls, lunch and learn
Program level issues. risks, and escalationPM team; MGH IHP CIFO; MGH IHP Director; MGH IHP Manager; IP Vice – ProvostTo define a risk, an uncertain event or condition that might have a positive/negative effect on the project’s deliverable goalsSemi-annuallyMeetings; risk document
Roll-out, change, and deployment announcementsPM team; MGH IHP CIFO; IPC manager; IPC Director; IHP clientsTo inform the teams of a new product/service; to discuss strategies of product releaseSemi-annually, more frequently as neededMeetings; discussion
Program decisionsPM team with Assistant to the CIFO; Campus Services Coordinator; MGH IHP Faculty; MGH IHP StaffTo inform the teams about executive leadership’s decisionsMonthly or as neededEmail lists; meetings
Lessons learnedPM team with all stakeholdersTo provide future project teams with information that can increase their effectiveness based on previous experienceOnce – at the end of the projectMeetings; lessons learned documented
Reviews for program performance. benefits realization, risks, change requests, and resourcesPM team; MGH IHP CIFO; MGH IHP Director; MGH IHP Manager; IP Vice – ProvostTo assess the success of the project in terms of value and contribution to the companyOnce – at the end of the projectMeetings; risk document
More related papers Related Essay Examples
Cite This paper
You're welcome to use this sample in your assignment. Be sure to cite it correctly

Reference

IvyPanda. (2021, August 8). Inter Process Communications Communication Plan. https://ivypanda.com/essays/inter-process-communications-communication-plan/

Work Cited

"Inter Process Communications Communication Plan." IvyPanda, 8 Aug. 2021, ivypanda.com/essays/inter-process-communications-communication-plan/.

References

IvyPanda. (2021) 'Inter Process Communications Communication Plan'. 8 August.

References

IvyPanda. 2021. "Inter Process Communications Communication Plan." August 8, 2021. https://ivypanda.com/essays/inter-process-communications-communication-plan/.

1. IvyPanda. "Inter Process Communications Communication Plan." August 8, 2021. https://ivypanda.com/essays/inter-process-communications-communication-plan/.


Bibliography


IvyPanda. "Inter Process Communications Communication Plan." August 8, 2021. https://ivypanda.com/essays/inter-process-communications-communication-plan/.

If, for any reason, you believe that this content should not be published on our website, please request its removal.
Updated:
This academic paper example has been carefully picked, checked and refined by our editorial team.
No AI was involved: only quilified experts contributed.
You are free to use it for the following purposes:
  • To find inspiration for your paper and overcome writer’s block
  • As a source of information (ensure proper referencing)
  • As a template for you assignment
1 / 1