Risk Management in Fly-Fishing and Construction Projects Case Study

Exclusively available on Available only on IvyPanda®
Updated:
This academic paper example has been carefully picked, checked and refined by our editorial team.
You are free to use it for the following purposes:
  • To find inspiration for your paper and overcome writer’s block
  • As a source of information (ensure proper referencing)
  • As a template for you assignment

Alaska Fly-Fishing Expedition

In this case, it is possible to think of the following risks: bad weather conditions, traumas, delays, damage to a boat, misroute (Larson & Gray 237). The most serious risk is bad weather conditions as the weather can hardly be foreseen. The weather can change even during the trip. These risks should be analyzed and taken into account.

Analysis of the Risks

Risk EventLikelihoodImpactDetection DifficultyWhen
Bad weather conditions344Entire period
Trauma321Entire period
Delays241Entire period
Damage to a boat251Entire period
Misroute242Entire period

Risk Response Matrix

Risk EventResponseContingency PlanTriggerWho Is Responsible
Bad weather conditionsRetainPut off the expedition.The weather sets in for more than a week.The developer of the expedition.
TraumaMitigate: Provide the necessary instructions on safety measures.Call for medical assistance, wait until the help comes.The condition of the injured worsens.The head of the group.
DelaysMitigate: Introduce fines for delays, or notify everyone that the group may leave without those who are late.If the delay is not crucial, it is possible to wait. If the delay is significant – leave without the one who is late.The delay is significant.The head of the group.
Damage to a boatMitigate: Make sure the boats are fine (choose a reliable rental company).Call for help. Continue the trip when the boat is mended, if possible.The boat cannot be repaired.The head of the group.
MisrouteMitigate: Choose reliable guides and ask about the route at the beginning of the trip.Contact the other group.The group cannot come to the arranged place to meet the other group.The guide and the head of the group

Silver Fiddle Construction

Potential Risks

It is possible to think of the following risks: bad weather conditions, gas furnace malfunctioning, supplies delays, rising prices, overload (Larson & Gray 237). Notably, the customer is ready to wait, so it is possible to postpone some works, which can help address possible risks. All these risks should be analyzed and taken into account.

Analysis of the Risks

Risk EventLikelihoodImpactDetection DifficultyWhen
Bad Weather Conditions332Initial part of the construction
Gas Furnace Malfunctioning232Installation
Supplies Delays242Entire Period
Rising Prices252Entire Period
Overload442Entire Period

Risk Response Matrix

Risk EventResponseContingency PlanTriggerWho Is Responsible
Bad Weather ConditionsRetainPut off the construction.The weather sets in for more than a week.The president of SFC.
Gas Furnace MalfunctioningMitigate: Work with reliable suppliers.Contact the supplier and get another system.The new system also malfunctions.The president of SFC.
Supplies DelaysMitigate: Sign contracts where fines for delays are included.Put off some works.The delay is too lasting (more than two weeks).The president of SFC.
Rising PricesRetainAddress the Czopeks and discuss what costs can be reduced and whether the cost can exceed the $500,000.The prices will continue going up.The president of SFC.
OverloadMitigate: hire someone to delegate some responsibilities.Put off some works as the Czopeks are ready to wait.The delay is too lasting (more than two weeks).The president of SFC.

Works Cited

Larson, Erik, and Clifford Gray. “Managing Risk.” Project Management, New York, NY, McGraw-Hill Companies, Inc., 2010, pp. 237–38.

More related papers Related Essay Examples
Cite This paper
You're welcome to use this sample in your assignment. Be sure to cite it correctly

Reference

IvyPanda. (2021, February 16). Risk Management in Fly-Fishing and Construction Projects. https://ivypanda.com/essays/risk-management-in-fly-fishing-and-construction-projects/

Work Cited

"Risk Management in Fly-Fishing and Construction Projects." IvyPanda, 16 Feb. 2021, ivypanda.com/essays/risk-management-in-fly-fishing-and-construction-projects/.

References

IvyPanda. (2021) 'Risk Management in Fly-Fishing and Construction Projects'. 16 February.

References

IvyPanda. 2021. "Risk Management in Fly-Fishing and Construction Projects." February 16, 2021. https://ivypanda.com/essays/risk-management-in-fly-fishing-and-construction-projects/.

1. IvyPanda. "Risk Management in Fly-Fishing and Construction Projects." February 16, 2021. https://ivypanda.com/essays/risk-management-in-fly-fishing-and-construction-projects/.


Bibliography


IvyPanda. "Risk Management in Fly-Fishing and Construction Projects." February 16, 2021. https://ivypanda.com/essays/risk-management-in-fly-fishing-and-construction-projects/.

If, for any reason, you believe that this content should not be published on our website, please request its removal.
Updated:
1 / 1