The Light Steel Frame Villa Project Essay

Exclusively available on Available only on IvyPanda® Made by Human No AI

Executive Summary

The objective of this report is to review different aspects of project management in order to grasp knowledge on the methodology and scope of the entire project, which is high-quality villas being constructed in the UAE. The project manager for the villa has made it his responsibility to track all the tasks to provide high-end finishing. The materials and labor source that is used in the project conforms to the Abu Dhabi construction requirements called the common building code of the UAE. The project is running in three phases and has recorded success at this point. The project is considered successful because the time and cost constraints are well balanced. Despite the existence of five risks, their impact is low, and mitigation strategies easy to impalements. The project has highly skilled personnel and is running for eighty-four days for each villa. However, there is a need to improve on the progress reporting strategy to ensure that all the stakeholders are satisfied.

Project Overview

The Light Steel Frame Villa project is yet to be completed and is based in the city of Abu Dhabi, in the UAE. The villas come in three and four bedrooms standalone houses that target middle-class families. The villa’s capacity includes a single sitting room, one kitchen, two floors, and a bathroom for each bedroom. The floor space for each villa is 400 square meters. The spacing was done to guarantee satisfaction on the side of families that are to occupy the villas. The villa project houses are made of concrete and light steel roofing. From the onset of the project, each villa has a fixed price tag, and customers do not have to worry about any increase in cost for the project. At present, the approximate costing for each villa is AED 360,000. The main components and the picture of the villa housing unit are summarized below:

  • Pilling and foundation in the form of basement
  • Concrete slab settlement
  • Villa frame covering an area of 400 square meters
Picture of a light steel villa.
Diagram 1: Picture of a light steel villa.

Methodology

In order to settle on the Light Steel Villa project, the team carried out series of searches and research of the currently or recently completed projects in the UAE. The team began by deciding to zero in on the construction industry, after which it was unanimously decided that a real estate project would be ideal. Several suggestions on current projects within the real estate sector were presented by the members, and the Light Steel Villa project was selected. The selection of this project was informed by the availability of information and accessibility of the current project implementation team. In order to approach the relevant authority to get permission to review the project, the team sent a mail to the project manager, who responded within three days.

After three meetings with the project manager, the team was granted permission to review the project from an insider perspective. In order to get the relevant information about the project, the team relied on direct observation with the guidance of the project manager and one of the project coordinators. The observations were done over a period of five days. The project manager was tasked with overseeing the entire villa development, with the project coordinator managing the daily tasks and activities for each section of the project. Interestingly, the project manager and coordinator were almost together every days the team was at the side. They seem to enjoy a cordial working relationship. The team could not avoid noticing the professionalism and accountability with which the two personnel acted whenever asked a question.

Project Definition

Project Objective

The primary objective of the project is to construct lightweight steel villas in the shortest time possible without waste of resources. The objectives of the Light Steel Frame Villa project is summarized in table 1 below:

ObjectiveDescription
To ensure that each villa is built efficiently and effectively within the project timeline.Through the creation of an efficient construction module, the time allocation from the beginning and the end of each villa construction was arranged to be systematic and fixed to avoid extra costs from delays.
To accomplish a standardized light steel villa within two months.This Light Steel Frame Villa project has the goal of developing a modularized and flexible construction approach to ensure that the cost and other requirements are done in an efficient manner.
To shorten the duration taken to construct the villa from laying the foundation to roofing and interior finishing.The interface adopted for the construction of the light steel villa is linked to the most sophisticated, ultra-modern, and price-friendly standards to the expected duration for completing the light steel villa.

As stated by the project manager, the above objectives conform to the project goal parameters of efficiency, cost management, and quality output. The strategy of the company is to provide affordable yet ultra-modern villas that are lightweight and of high-end quality.

Project Categorization

As indicated in the project development blueprint, the owners of the Light Steel Frame Villa project were interested in creating a new housing structure that is affordable, lightweight, and durable in the expansive Abu Dhabi real estate market. The idea was to create a completely new idea on the structural capability of a housing project that customers would be looking forward to buying and comfortably live in. In order to achieve this, the project owners decided to come up with an estimated cost for each villa at about AED 360,000. In order to conceptualize the project, the following milestones were identified by the project owners as guidance to achieving the primary objective of quality, affordable and lightweight villas.

  • Get approval from architectures and relevant authorities to give the project the green light and general acceptance by the end-users.
  • Create detailed documentation and sketches of the villa to ensure that the end product is a replica of the initial plan.
  • Establish a legal tendering process to take care of the interests of the project owners and end-users.
  • Negotiate for good offers on the land where the project is to be carried out, including due diligence.
  • Track the element of quality control and assurance to ensure that the project outcome is satisfactory to all the stakeholders.

In order to accomplish the above milestones, the project owners, through the project manager, adored the following approaches.

  • All aspects of documentation are micro-managed by the project manager, who doubles up as the primary contractor.
  • The aspect of licensing and approvals was allocated to the sub-contractor, who doubles up as the project coordinator. This means that the sub-contractor will be responsible for any faults identified by the client that are related to licensing and approvals.
  • The progress in the villa project is counted after every week to ensure that the fixed pricing is not changed.

In order to successfully accomplish the above approaches, the functional and system scopes of the project were integrated and run concurrently to ensure that any in-scope and out-of-scope elements are micro-managed. Under the system scope, the aspects of benefits, general ledger, human capital, and efficiency matrices were centralized in terms of management (Snyder, 2013).

Project Organizational Structure

Execution of the Light Steel Frame Villa project was carried out in a four-stage strategy to incorporate the output deliverables. Specifically, the Gantt chart was employed to track the milestones under which the organizational structure functioned. Specifically, the organizational structure comprised of the costing for the personnel, expectations, and roles assigned to each team. The organizational structure of the project involved procurement of the necessary personnel, logistical support, deployment of technical support, and constant tracking of the stakeholder to guarantee smooth operations as summarized in the schedule chart below:

MilestoneStart DateCompletion Date
Initiation
Project Charter20thJan29thJan
Approve Project Charter30thJan5thFeb
Hold Kick Off for Project Initiation Planning5thFeb6thMar
Planning (High Level)
Project Initiation Plan6thJan7thFeb
Approve Project Initiation Plan27thFeb4thMarch
Hold Kick Off for Detail Planning7thMarch16thMarch
Planning (Detail)
Project Plan (Detailed)9thJan10thJan
Baseline Schedule10thJan12thJan
Approve Baseline Schedule11thJan12thJan
Hold Kick Off for Executing the Project13thJan14thJan
Executing and Controlling
Developing the restoration logistics14thFeb15thFeb
Completion of the workshop and technological installations14thFeb16thFeb
Closing
Transition to Steady State-Project Close-Out Report18thMarch18thMarch
End of Project Review Report (Lessons Learned)20thMarch20thMarch

In order to smoothly achieve the four phases, each phase of the project was carried out concurrently to reduce potential risks from disorganization in the organizational structure. Besides, the following roles and responsibilities were assigned to different personnel involved.

Project Manager

WhoRole% Time Required per villa
Project management400 hours
Project Responsibilities
  • Keep abreast of all major project activities
  • Provide approval for all major scope changes
  • Provide signoff to approve the project to move forward to succeeding phases

Steering Committee

WhoRole% Time Required
Project supervisorAdvisory role720 hrs
Project managerAdvisory role720 hrs
Site consultantAdvisory role720 hrs
Project Responsibilities
  • Act individually and collectively as a vocal and visible champion for the project
  • Provide direction and guidance to the project
  • Help resolve issues and policy decisions

Project Supervisor

WhoRole% Time Required
Project supervision850 hrs
Project Responsibilities
  • Manages the project scope, schedule, and budget
  • Communicate status/issues as identified in the Communication Plans
  • Provide performance feedback to team members and manage risks
  • Gain Project Acceptance
  • Archive Project Information

Project Constraints

The ratio method was used to recognize the estimated costing, time, and scope from the organizational structure above. Basically, the ratio method observes the top-to-down strategy of estimation within low margins of error. The time taken against the cost for the Light Steel Frame Villa project is summarized in the table below from the Work Breakdown Structure.

Work Breakdown Structure
Work Breakdown Structure

From the work breakdown structure, the time, work ratio, and cost constraints are summarized in the table below:

S.NOPosition in WBSWork ratio (%)Cost based on work ratio(AED)Estimated cost(Budget)
1.2.1.10.51,8002,000
2.2.1.21.76,1206,000
3.2.1.312.946,44046,000
4.2.2.14.716,92017,000
5.2.2.23.211,52011,000
6.2.2.33.512,60013,000
7.1.1.12.17,5607,000
8.1.1.23.914,04014,000
9.1.1.39.935,64036,000
10.1.2.11139,60039,000
11.1.2.210.437,44037,000
12.1.2.32.48,6407,000
13.3.1.17.326,28026,000
14.3.1.21.55,4006,000
15.3.1.33.412,24012,000
16.3.1.44.817,28021,000
17.3.2.17.828,08028,000
18.3.2.24.716,92017,000
19.3.2.34.315,48015,000
Total100%360,000360,000

The approximations in the above table were made based on past experiences for a similar project against work ratio. Thus, the value estimated from duration was twelve weeks, which is equivalent to eighty-four days. The allocation of time for each activity against cost is summarized in the table below:

S.NOPosition in WBSActivitiesDuration
(In days)
Cumulative DaysCost
(AED)
Cumulative cost
1.2.1.1Cleaning site222,0002,000
2.2.1.2Leveling246,0008,000
3.2.1.3Concrete base61046,00054,000
4.2.2.1Fixing concrete beams61617,00071,000
5.2.2.2Fixing concrete channels52111,00082,000
6.2.2.3Joist fitting42513,00095,000
7.1.1.1Electric wiring2277,000102,000
8.1.1.2Wire Installations43114,000116,000
9.1.1.3AC Installations53636,000152,000
10.1.2.1Water system64239,000191,000
11.1.2.2Drainage system64837,000228,000
12.1.2.3Testing installations1497,000235,000
13.3.1.1Covering room walls65526,000261,000
14.3.1.2Covering Toilet tiles2576,000267,000
15.3.1.3Kitchen platform25712,000279,000
16.3.1.4Covering ceiling66521,000300,000
17.3.2.1Wall plastering67128,000328,000
18.3.2.2Wall painting47517,000345,000
19.3.2.3Carpeting27715,000360,000
T.D = 77T.D = 77T.C = 360,000T.C = 360,000

Risks/Challenges and Mitigation

The risks identified include earthquake (Risk 1), excessive temperature (Risk 2), electrocution (Risk 3), corrosion (Risk 4), and ignorance from the end-user (Risk 5). In terms of probability of occurrence, Risk 1 is low, thus can be prevented through the use of a special layer of protection. Risk 2 also has a low probability of occurrence and can be mitigated through improvement in the basement design. Although the probability of Risk 3 occurring is low, there is a need to insulate the steel pillars since its impact would jeopardize the project from a safety perspective. The probability of experiencing Risk 4 and Risk 5 are equally low and could be mitigated through the insulation of the beams to avoid corrosion and prescribing maximum load to avoid villa collapse, respectively. As a result of the low probability of occurrence of the five risks, the ideal strategy for mitigation would be to transfer the risks through the proposed avoidance strategies. This is summarized in the risk register below:

Probability of having Risk1, P =LowProbability of having Risk2, P =Low
The impact from Risk1, I=Very HighThe impact from Risk2, I=Very High
Estimating Significance of Risk1, E = P*IHighEstimating Significance of Risk2, E = P*IHigh
The action of prevention, AP =Using special protection layerThe action of prevention, AP =The basement should be designed to collapse independent of the whole structure.
Cost of correcting with actionCA = AED 40000Cost of correcting with actionCA = AED 4000
Probability of having Risk3, P =LowProbability of having Risk4, P =Low
The impact from Risk3, I=Very HighThe impact from Risk4, I=Very High
Estimating Significance of Risk3, E = P*IHighEstimating Significance of Risk4, E = P*IHigh
The action of prevention, AP =Insulating properly and using fusing boardsThe action of prevention, AP =Water insulating cover on beams
Cost of correcting with actionCA = AED 16000Cost of correcting with actionCA = AED 5000
Probability of having Risk5, P =Low
The impact from Risk5, I=Very High
Estimating Significance of Risk5, E = P*IHigh
The action of prevention, AP =They are prescribing the maximum load.
Cost of correcting with actionCA = AED 40000

Changes in the Project

Fortunately, there were no changes in the project since the level of preparedness and costing against duration matched with the personnel output.

Success and Failure

Since the project is still in progress, it is difficult to decide whether it has failed or succeeded. However, considering the current level of progress against the timeline for each phase of the project, it can be declared as successful since the time, and cost constraint estimation have not been passed. Besides, the current phase of the project is already meeting the objective since no changes have been recorded for materials, costing, or any other project milestone. The success of the project was measured using the work ratio of a similar past project against the current project, and the result was positive (Snyder, 2013). We support the work ratio approach since it incorporates the constraints against each activity in each phase of a project to monitor progress.

Recommendation

Despite the current successes and balance between the project constraints, there is a need for the project manager to encourage the project-driven organization structure to ensure that needs of customers and other stakeholders are guaranteed (Basu, 2016). Although the current organizational structure is functional, the excessive controls placed in the hands of the project manager and coordinator might result in a rigid framework for decision-making in a dynamic environment such as the Abu Dhabi real estate sector. Thus, the proposed organizational structure would align the current objectives to quality and efficiency parameters in case of any future risk that is currently hidden (Microsoft Corporation, 2012). Besides, due to the dynamics in the real estate industry, the current project cycle should be adjusted to be flexible to accommodate any future changes since the current model has fixed costing and timeline (Rodrigues & Crispim, 2014). In addition, despite the low probability of risk occurrence, there is a need to avoid the currently identified risks since their cost implications are more than 10% of the cost of each completed villa (Burke, 2013). Through progressive management and due diligence, the end-user might not be subjected to any of the risks identified.

References

Basu, R. (2016). Managing projects in research and development. London, UK: Routledge.

Burke, R. (2013). Project management techniques (2nd ed). New York, Ny: Burke Publishing.

Microsoft Corporation. (2012). Web.

Rodrigues, L., & Crispim, J. (2014). The project risk management process, a preliminary study. Procedia Technology, 16 (4), 943-949.

Snyder, C. (2013). A project manager’s book of forms: A companion to the PMBOK guide (2nd ed.). Hoboken, ST: Wiley and Sons.

More related papers Related Essay Examples
Cite This paper
You're welcome to use this sample in your assignment. Be sure to cite it correctly

Reference

IvyPanda. (2021, May 30). The Light Steel Frame Villa Project. https://ivypanda.com/essays/the-light-steel-frame-villa-project/

Work Cited

"The Light Steel Frame Villa Project." IvyPanda, 30 May 2021, ivypanda.com/essays/the-light-steel-frame-villa-project/.

References

IvyPanda. (2021) 'The Light Steel Frame Villa Project'. 30 May.

References

IvyPanda. 2021. "The Light Steel Frame Villa Project." May 30, 2021. https://ivypanda.com/essays/the-light-steel-frame-villa-project/.

1. IvyPanda. "The Light Steel Frame Villa Project." May 30, 2021. https://ivypanda.com/essays/the-light-steel-frame-villa-project/.


Bibliography


IvyPanda. "The Light Steel Frame Villa Project." May 30, 2021. https://ivypanda.com/essays/the-light-steel-frame-villa-project/.

If, for any reason, you believe that this content should not be published on our website, please request its removal.
Updated:
This academic paper example has been carefully picked, checked and refined by our editorial team.
No AI was involved: only quilified experts contributed.
You are free to use it for the following purposes:
  • To find inspiration for your paper and overcome writer’s block
  • As a source of information (ensure proper referencing)
  • As a template for you assignment
1 / 1