Building Cordless Vacuum Cleaner Project Coursework

Exclusively available on Available only on IvyPanda® Made by Human No AI

Introduction

Project management involves a series of activities which must follow each other in a sequential way; to interpolate the trend, there is the use of charts and net work diagrams. This paper analyses a project of Building a cordless vacuum cleaner

The Bestclean is a new cordless vacuum cleaner. An analysis of the task of building the Bestclean reveals the following list of relevant activities, their immediate predecessors, and their duration.

The following are the data for the project;

JobDescriptionImmediate PredecessorsNormal Time(Weeks)
AProduct Design6
BMarket research Plan2
CManufacturing and engineeringA3
DPrototypeA5
EMarketing BrochureA3
FCost EstimateC2
GTestingD3
HMarket surveyB,E4
IPricing and forecastH2
JFinal reportF,G,I2

Network diagram for the project

Network diagram for the project

Network analysis

A net work is a diagrammatical representation of a project which interpolates the various activities that are to take place during a program. It has a representation of activities as they follow each other. it shows which activity follows another and which activity can follow either two or more projects.

It does the task by the use of activity-on-node, which are used to represent predecessor activities and successor activities ( Walkenbach, 1997).

Critical path

This is the longest path in a project; it denotes the longest duration that a project will take. In our case the critical path is through,

The critical path is through

The total time is 6 + 3 + 4 + 2 + 2 = 17 weeks

The following are the activities along the critical path;

The activities along the critical path

Critical path have no slack or float time. This means that any change on the duration of the crystal path activity will result to a change in the overall duration of the project. If the time is added or there an adoption of some technology that makes the path shorter, they will make the entire project shorter.

Another characteristic of critical path is that there can be more that one critical path in one project. When the critical path of one path is altered it automatically alters the path of the entire project (Pons, 2008).

CRITICAL PATH Gantt chart

Critical Path Gantt chart

Project duration

This is the period that a certain project is likely to take from start to the finish. In a well managed program, project duration is the duration through which critical path follow. This is because activities along this path have a float time of Zero. Any delay on these activities result to a delay of the entire project activities.

Floats of the non-critical activities

These are functions that are not in the critical path. They can be delayed for a certain period of time and still the project finish in the right time. There is a maximum time that the activities can be delayed, the period is referred to as slack time or float time.

There are three types of floats:

Free floats

This is the maximum period of time that a single project activity can be delayed without affecting the earliest start time of the following activity.

Total float

This is the total delay time that a single activity in the non critical path can be delayed without affecting the duration of completion of the project.

Project float

This is the total duration that a project can be delayed and still ensuring completion at the customers expected time.

In our diagram above, the non critical paths are;

START – A – D — G — J

START – B — H – I – J and

START — A – C – F – J

To calculate the float time of each path, one needs to calculate the time taken in the path then you subtract it from critical path;

Uncritical path 1

START – A – D — G — J duration is 16

Float time is 17-16 = 1 week

Uncritical path 2

START – B — H – I – J duration is 10

Float time is 17-10 =7 weeks

Uncritical path 3

START — A – C – F – J

Float time is 17-13 = 4 Weeks

Knowing the amount of float time helps in resource allocation where the project manager can know the activities that he can hold for a certain time due to a certain reason. One of the reasons that can make a project to be held momentarily is lack of funds or employees (McComb, Kennedy, Green, & Compton, 2008).

Early-start Gantt chart and resource profile for the project

The chart contain the earliest start Gantt chart; it follows START – B — H – I – J duration is 10

The following are the activities:

The activities

Early-start Gantt chart and resource profile for the project

Resource profile for the project

Resource profile for the project is interested on how resources will be distributed in various projects. There are projects which allocation can be delayed (non critical path activities) and there are those which resources must be available if the project have to be completed in good time. They are the activities along the critical path.

In case there is a deficit, then in our case;

Uncritical path 1 (START – A – D — G — J) can be delayed for one week; uncritical path 2 (START – B — H – I – J) can be delayed for a total of 7weeks and Uncritical path (START — A – C – F – J) can be delayed for 4 weeks.

Using the critical path, a project manager is able to give the longest period that a certain project can take. If the project is required at an earlier or later date, then network diagrams are used in adjusting the duration (Kumar, 2005).

Conclusion

Using Gantt chart and network diagram assists a project manager to understand the processes that the project will undertake. When analyzed, those activities which can be delayed for a reason or another are sort. They are managed well not to ensure that they don’t affect the completion of the project in time. Float time are utilized in managing time which a project can be delayed.

Using the critical path, a project manager is able to give the longest period that a certain project can take. If the project is required at an earlier or later date, then network diagrams are used in adjusting the duration.

Bibliography

Kumar, P. (2005). Effective Use of Gantt chart for Managing Large Scale Projects Cost Engineering, 47(7), 14-21. Retrieved from Business Source Complete database.

McComb, S., Kennedy, D., Green, S., & Compton, W. (2008). Project team effectiveness: the case for sufficient setup and top management involvement. Production Planning & Control, 19(4), 301-311. doi:10.1080/09537280802034059.

Pons, D. (2008). Project management for new product development. Project Management Journal, 39(2), 82-97. doi:10.1002/pmj.20052.

Walkenbach, J. (1997). Gantt charts in Excel. PC World, 15(12), 386. Retrieved from MasterFILE Premier database.

More related papers Related Essay Examples
Cite This paper
You're welcome to use this sample in your assignment. Be sure to cite it correctly

Reference

IvyPanda. (2019, June 7). Building Cordless Vacuum Cleaner Project. https://ivypanda.com/essays/project-planning-and-control/

Work Cited

"Building Cordless Vacuum Cleaner Project." IvyPanda, 7 June 2019, ivypanda.com/essays/project-planning-and-control/.

References

IvyPanda. (2019) 'Building Cordless Vacuum Cleaner Project'. 7 June.

References

IvyPanda. 2019. "Building Cordless Vacuum Cleaner Project." June 7, 2019. https://ivypanda.com/essays/project-planning-and-control/.

1. IvyPanda. "Building Cordless Vacuum Cleaner Project." June 7, 2019. https://ivypanda.com/essays/project-planning-and-control/.


Bibliography


IvyPanda. "Building Cordless Vacuum Cleaner Project." June 7, 2019. https://ivypanda.com/essays/project-planning-and-control/.

If, for any reason, you believe that this content should not be published on our website, please request its removal.
Updated:
This academic paper example has been carefully picked, checked and refined by our editorial team.
No AI was involved: only quilified experts contributed.
You are free to use it for the following purposes:
  • To find inspiration for your paper and overcome writer’s block
  • As a source of information (ensure proper referencing)
  • As a template for you assignment
1 / 1