The Issues of Project Closeout Essay

Exclusively available on IvyPanda Available only on IvyPanda

Introduction

Project-close-out marks the finalization of all project activities in all phases. The objective is to close a project in a formal way followed by making a transfer of the cancelled or otherwise completed project to the owners. Large project-closeout techniques may apply upon the completion of each phase. However, various retainage issues may emerge during project closeout. This paper discusses these issues.

We will write a custom essay on your topic a custom Essay on The Issues of Project Closeout
808 writers online

Importance Closeout in Construction Contracts

Projects are constrained by time and monetary resources. In their execution, various challenges that cause financial risks and delays may occur. To ensure that such risks do not occur in similar projects in the future, construction projects must reach the crucial and final step of closeout (Koffman and Macdonald 107). At this stage, a project is assessed, documented lessons learned, completion realized, and guidelines provided on the best practices that need adoption in future similar projects. This strategy helps in avoiding repetition of mistakes or risks that could be mitigated even before a project has been initiated.

Effects of Certificate of Completion or Substantial Completion on Retainage

Certificate of completion or substantial completion serves as a conclusive document indicating that the employer, through the contract administrator, is satisfied with works executed and quality of materials and goods supplied for the whole project or part of the project (Dentons par.1). Retainage acts as the shield against payments for defective works, solvency risk of contracting parties, and overpayments for work performed (Bausman 1). Certificate of completion or substantial completion concludes that any issues of duty of care, concerns of breach of contract, and even statutory duties have been taken into full consideration in the work segments that it is issued for or for the whole projects. Upon issuance of the certificates, any retainage held by the employer is inconsistent with the purpose for which retainage is set to achieve.

Disputes in Beneficial Use of a Project

Construction projects require all parties to understand their responsibilities as specified in the contracts. However, hotspots of dispute may emerge between the contractor and the owner after the proprietor begins a beneficial use of the project due to the parties not understanding their responsibilities. For example, after the project has progressed to a stage where it is suitable for occupation or meets the criteria for use as intended, substantial completion issues may become hotspot disputes. Disputes may emerge from withholding of a contractor’s funds upon failure of the owner to recognize substantial completion. Disputes arise when the contractor treats a project as less substantially completed.

Certificate of Substantial Completion and Liquid Damages

Upon substantial completion, the owner has no right for assessing liquidated damages. Indeed, liquidated damages comprise one of the sources of disputes between the contractor and the owner (SBC/Q 55). Insurance of certificate of substantial completion erodes the right of the owner to collect any liquidated damages associated with late completion since the project can serve the needs for which it was intended (Eggleston 26).

Releasing Final Retainage Funds

After a project has been completed, the owner has an obligation for releasing the final retainage funds. This stage occurs upon the issuance of certificate of occupation followed by certificate of completion (Designing Buildings par.5). Warranties are also necessary to provide the surety that the project will perform as intended for a given period without the occurrence of defaults, which the contractor remains obliged to rectify them at no extra cost if they occur even after the retained funds have been disbursed.

Conclusion

Construction projects involve payment for product before it has been successfully delivered to the owner. They have various risks, including payment for poor quality work, and continued solvency of the contracting parties, and hence the need for incorporating retainage clauses in construction contracts. However, the clause may attract disputes between the parties.

1 hour!
The minimum time our certified writers need to deliver a 100% original paper

Works Cited

Bausman, Dennis. Retainage Practice in the Construction Industry, New York, NY: Clemson University, 2004. Print.

Dentons. The High Court Considers the Final Certificate Conclusively Provisions of the JCT, 2015. Web.

Designing Buildings. , 2015. Web.

Eggleston, Brian. Liquidated Damages and Extensions of Time: In Construction Contracts, New York, NY: John Wiley & Sons Ltd, 2009. Print.

Koffman, Laurence, and Elizabeth Macdonald. The Law of Contract, Oxford: Oxford University Press, 2007. Print.

SBC/Q. Standard building contracts with quantities. London: Sweet &Maxwell, 2011. Print.

Print
Need an custom research paper on The Issues of Project Closeout written from scratch by a professional specifically for you?
808 writers online
Cite This paper
Select a referencing style:

Reference

IvyPanda. (2022, April 18). The Issues of Project Closeout. https://ivypanda.com/essays/the-issues-of-project-closeout/

Work Cited

"The Issues of Project Closeout." IvyPanda, 18 Apr. 2022, ivypanda.com/essays/the-issues-of-project-closeout/.

References

IvyPanda. (2022) 'The Issues of Project Closeout'. 18 April.

References

IvyPanda. 2022. "The Issues of Project Closeout." April 18, 2022. https://ivypanda.com/essays/the-issues-of-project-closeout/.

1. IvyPanda. "The Issues of Project Closeout." April 18, 2022. https://ivypanda.com/essays/the-issues-of-project-closeout/.


Bibliography


IvyPanda. "The Issues of Project Closeout." April 18, 2022. https://ivypanda.com/essays/the-issues-of-project-closeout/.

Powered by CiteTotal, best bibliography generator
If you are the copyright owner of this paper and no longer wish to have your work published on IvyPanda. Request the removal
More related papers
Cite
Print
1 / 1